| Quote |
|---|
| But a category represents related tasks that could be done by 2 different resources and each should not see the other. |
Permissions can be set for Task Groups, not for separate Tasks. So you can create category Project 1, and its subcategories John's Tasks and Mark's Tasks. When the task is general you can assign it to Project 1 category and they both will see it, when the task specific you can assign it either to John's Tasks or to Mark's Tasks.
| Quote |
|---|
| Some tasks are dependent upon other tasks so it should be able to be specified as well and be able to view dependency. |
I see, but how exactly would you like the program to show this dependency, ex.: simply a text that tells that this task depends on that task, or possibility to set a link to the dependent task, or something else?
| Quote |
|---|
| I see. But can it be done graphicly in the calander? |
Not sure I understand. Could you explain it in more details with an example?