We use the 'Estimated time' field on all our tasks to be able to create reports that give us an idea of the total workload. This works fine as long as we specify the estimated times in hours. When specifying this value in days a day in Taskmanager is counted as 24 hours, while our users usually mean work days, which are 8 hours. This makes our reports unusable.
The same issue exists for 'Week', which also counts 24 hours in a day, and 7 days in a week instead of 5 work days. This way 168 hours are accounted for, instead of 40...
Can you translate the 'day'-value to 8 hours instead of 24 hours, or provide another solution to specify the number of hours in a day? Same question for the week-value.
Maybe you can add 'Work day' (= 8 hours) and 'Work week' (= 40 hours) as new time specifiërs. (Optionally you could give us the possibility to specify the numbers of hours in a 'Work day' and 'Work week' in the programs general preferences)?
Thanks a lot,
Geert